Portfolio

FedEx Distribution Center - Missouri City, TX

365,000 Square feet building pad, 776,000 square feet concrete paving area, and a 297,796 square feet wet bottom detention pond for the development retention. Grade building pad area with 68,000cyds of imported select fill to 6” below finish floor. Paving area is graded with onsite material and stabilized with lime slurry. Excavate detention pond and used material onsite.

Owner: FedEx

GC: Rosenberger Construction, LLC.

iFly - Oak Ridge North, TX

Construction of a 5,000sf indoor skydiving facility and associated site work. Scope of work included backfilling around the basement construction. Stabilize paving area and placement of crushed base in preparation for asphalt by others

Owner: iFly

GC: Structura Inc.

Lightning Logistics Distribution Center - Houston, TX

66,000sf building pad, 65,000sf concrete paving area, 91,000sf crushed concrete lay down area, and a 22,000sf detention pond for an existing facility that remained operating at 100% capacity throughout construction. Grade building pad area with onsite material to 6” below finish floor. Paving area is graded with onsite material and stabilized with TruBln. Lay down yard was cleared and graded with onsite material, stabilized with TruBln, and then placement of a geo fabric and crushed concrete for the finished surface. Excavate detention pond and use material onsite.

Owner: Lightning Logistics

GC: LEAD Constructionpa

Hunting Energy Services Pipe Threading Facility - Baytown, TX

Construction of 40 acres with four buildings totaling over 120,000 sf of building pads, 350,000sf paving area, and 310,000sf of GS200. Building pad scope includes over excavating existing soils to allow for a 4’ thick building pad of imported select fill. Grade paving areas with onsite material and stabilization of paving area with lime slurry. Grade areas to receive 12” of GS 200 material and stabilize with lime slurry. Place GS200 material in 6” lifts, compact and finish grade final lift. Grade grass areas to sheet drain per the design.

Owner: Hunting Energy

GC: Burton Construction

Interstate Commerce - Houston, TX

410,000sf building pad with 567,000sf of paving and sidewalks. Scope of work included clear and burn trees and brush on entire 75acre development. Building pad included placing onsite select fill 4’ thick. Stabilize paving areas with TruBln. All earthwork was completed with GPS machine control equipment.

Owner: Interstate Commerce

GC: Burton Construction

Tellepsen Industrial - Pasadena, TX

20,000 sf Office/production area including over 50,000 sf of paving and sidewalks. Building pad scope includes over excavating existing soils to allow for a 4’ thick building pad of imported select fill. Stabilization of paving area with lime slurry.

Owner: Carson Industrial

GC: Slate Construction

Walker Houston Headquarters Building - Houston, TX

30,000sf building pad with 40,000sf of paving and sidewalks. Scope of work included clear and haul off trees and brush. Building pad included stabilization of onsite material and placing a minimum 24” thick building pad. Use Lime Slurry to stabilize the paving area. Excavate the detention pond and use on site. All earthwork was completed with GPS machine control equipment.

Owner: Walker Engineering

GC: Burton Construction

iFly Bunker Hill - Houston, TX

Construction of a 5,000sf indoor skydiving facility and associated site work. Scope of work included over excavating 18’ below grade to allow for the basement construction. Prior to final excavation MSC assisted in installing the de-watering system to 25’ below grade to allow for a safe excavation. Over excavated material had to be removed from the site. Stabilization of paving area with TruBln.

Owner: iFly

GC: Structura, Inc.

Memorial Hermann Expansion - Katy, TX

42,000 sf Hospital expansion with paving and demo of existing campus parking. Scope of work included demo of over 115,000sf of existing concrete paving and haul off site. Building pad scope included over excavate 5’ below finish floor to allow for construction of foundation and then backfill with moisture conditioned onsite material to 18” below finish floor; the final 12” of fill was select fill. Stabilization of paving area with TruBln.

Owner: Memorial Hermann

GC: Rosenberger Construction, LP.

Memorial Hermann MOB- Katy, TX

29,000 sf Medical Office Building with paving and demo of existing campus parking. Scope of work included demo of over 68,000sf of existing concrete paving and haul off site. Building pad scope included 12” of select fill over existing subgrade. Stabilization of paving area with TruBln.

Owner: Memorial Hermann

GC: Rosenberger Construction

Karbach - Houston, TX

22,000 sf Brewery expansion and 21,000sf paving and sidewalks. Scope of work included demo of existing concrete paving and removal of underground piers. Building pad scope included 12” of select fill over existing subgrade and the over excavation for the mat foundation in the tank area. Stabilization of paving area with lime slurry. Excavation of detention pond was included. All earthwork completed with GPS machine controlled grading.

Owner: Karbach Brewing Co.

GC: Camden Construction, Inc

Christian Brothers Automotive Corporate - Houston, TX

25,000 sf Office building with over 60,000sf paving and sidewalks. Building pad scope includes stabilizing the top 12” in place with TruBln and grade to +/-.10’. Paving area includes grading the existing soils and hauling off the excess material. Paving subgrade was stabilized with TruBln. Two detention ponds were excavated and material was hauled. All earthwork completed with GPS machine controlled grading.

Owner: Christian Brothers Automotive

GC: A&F General Contractors

Imperial Linens

58,000 Square feet office/production area including over 50,000 square feet of paving and sidewalks. Building pad scope includes over excavating existing soils to allow for a 6’ thick building pad of lime stabilized material. The paving area includes stabilizing with lime slurry. All earthwork completed with GPS machine controlled grading. Expansion of bates lane included in scope of work.

Owner: Imperial Linens

GC: Rosenberger Construction, LP.

CorPro Building Addition

Building expansion and construction of detention pond while existing facility remains operational. Construction of building pad includes moisture condition of material excavating onsite detention pond.

Owner: CorPro

GC: Slate Construction, LLC

Delta Rigging

30,000 Square feet office/warehouse with paving and crushed concrete laydown yard. Earthwork scope includes over excavation of building pad and stabilization of onsite material to allow for a 5’ thick pad. Lime stabilization in the paving area 8” thick. Crushed concrete yard includes grading, lime stabilization, and placement of 8” of crushed concrete base. Final grading utilizing GPS machine control.

Owner: Delta Rigging

GC: Structura, Inc

Invensys Headquarters - Houston, TX

11,000 s.f. Office Expansion with paving and site grading. Earthwork scope importing 1,400 c.yds. of select fill for the building area and excavating 1,500 c.yds. from paving area and exporting off site. Stabilization of paving area with TruBln.

Owner: Invensys Systems

GC: Structura, Inc.

Flow Controls

17,000 s.f. Office/Warehouse with paving and detention pond. Earthwork scope includes 3,000 c.yds. of select fill for the building area and excavating onsite detention pond. Detention pond cut used for paving fill.

Owner: Flow Controls

GC: Double D Industries

Suhm Springs - Houston, TX

Fine grade 9 acre site to receive landscaping and sidewalks. The existing concrete paving had to be protected and all debris to be kept off parking area to minimize any tracking of soils into public right-of-way and/or public drainage system.

Owner: Suhm Springs

GC: Rosenberger Construction